Kargman Basement — Wednesday 8/12

154 E 62nd St, Manhattan · crew days Wed–Fri · updated 8/11 night

Pull from the attic

Pull from the garage

⛔ Do NOT take the old table saw

Fence is bad — that's why the new one was bought. It's just wasted van space. Leave it.

Buy / pick up

Van startup — order matters

1. Start the engine → 2. inverter on → 3. battery charger on.
Inverter before engine drains the van's main batteries.

Wednesday — who's on what

Justin
  • 5:00 AM video chat with Matej
  • Attic + garage pull, then Smithtown for the saw
  • Pre-wire cabinetry — Harry's closet
  • Start wiring the third-floor bathroom modules
  • Assist Joe — rack migration + punchdowns
Joe
  • Rack migration + punchdowns with Justin
  • Third-floor tasks · closet cabinetry pre-wire
  • Bathroom modules · start wiring the main rack
Matej
  • Trim the rack door FIRST (stays clear of the others)
  • Cabinet doors + trims once the saw lands — seamless
  • Hand-tool support for Joe on the third floor

Questions

Ask Matej first if you're unsure — direct, on the walkie or the 5am call. Anything else, call Tony.